A dump truck has a capacity of 10 cubic meters. If the soil swell is 20%, how many bank cubic meters (BCM) of soil can the truck carry in one load?
22
Which of the following is the primary purpose of 'Compaction' in construction works?
23
In a construction project, what is a 'Change Order'?
24
What is the function of a 'Vibrator' when placing fresh concrete in deep columns or walls?
25
A construction activity has an early start (ES) of day 5 and a duration of 10 days. If its late finish (LF) is day 20, what is the total float of this activity?
26
What is the purpose of 'Shoring' in a building renovation or excavation project?
27
Which of the following is NOT a characteristic of a 'Critical Path' activity in a project schedule?
28
In concrete technology, what does the 'Water-Cement Ratio' primarily determine?
29
What is the primary function of a 'Trench Box' (or shield) in an excavation operation?
30